America drop lock Frame Scaffolding
Advantages
1) Gate steel pipe scaffold geometric size standardization.
2) Reasonable structure, good performance, full use of steel strength, high carrying capacity.
3) Easy assembly and disassembly in construction, erection of high efficiency, save time and labor, safe and reliable, affordable.
Adaptability
1) Build stereotypes scaffolding
2) For the beam, plate frame support frame (to withstand vertical load);
3) Construction of the activity table;
Erection requirements
1) Door scaffolding base must be compacted, and should do a good job drainage slope, to prevent water
2) The door scaffolding erection order: the basis of preparation → place the plate → place the base → vertical two single-chip mast → install the cross bar → install the scaffolding → as a basis for repeated installation of mast, cross bar, scaffolding process The
3) Door steel scaffolding should start from one end to the other end erected, step scaffolding should be carried out in the next step scaffolding erection. The erection direction is opposite to the next step.
4) Each step scaffolding erection, should be inserted in the end of the base of the two mast, and then installed on the cross bar fixed, lock the lock, and then erected after the mast, each take a pin, then install the cross And lock pieces.
5) Scaffolding must be set up with a reliable link to the building.
6) Door button steel scaffolding should be set on the outside of scissors, vertical and vertical should be set continuously.